The calculation of Work, Duration, and Units

The calculation of Work, Duration, and Units


1 day Duration = 8 hours Work /100% Units

Units= Units are the percentage of a resource’s workday
For example, if you want Joe to work half-time on a task, you would assign him at 50 percent Units.
If a resource’s workday is eight hours and he or she is assigned to work on a task at 100% Units (for eight hours of work), then the Duration is eight hours (one day by default).
Work= NO OF hours
Duration: - no of days to complete the task.

If a resource’s workday is four hours and he or she is assigned to work on a task at 50% Units (for eight hours of work), then the Duration is eight hours (one day by default).